§ 10-55. Industrial construction, certificate of occupancy, expedited procedure.  


Latest version.
  • (a)

    A certificate of occupancy for an industrial use in an industrial zoning district that was permitted through the expedited process shall be issued in accordance with this section. An application for a certificate of occupancy following the expedited process shall include the following submittals:

    (1)

    A letter stating that the building has been completed and that a certificate of occupancy is requested.

    (2)

    A sworn affidavit from the inspector or inspection agency that the building has been constructed in accordance with the city adopted building codes.

    (3)

    Certified copies of all inspection reports and notices.

    (4)

    One set of record as-built drawings stamped and sealed by a registered design professional.

    (b)

    Upon receipt of a completed application and all required submittals, the building official shall make a determination as to whether all provisions of the city's adopted building codes, this section, and other applicable laws have been met. If the building official is able to make such a finding, then a certificate of occupancy shall be issued immediately upon payment of any applicable fees. If the building official is unable to make such a finding, then he shall state the reasons in writing.

( Ord. No. 3414, § 4, 9-10-2018 )